Castelion signs Air Force missile contracts as Rio Rancho plant ramps up
The company secures two new agreements for counter-air missiles and plans to produce Blackbeard weapons for F-16 jets at its Sandoval County facility.
By Paula Delgado ·

Castelion has secured more than $1 billion in contracts with the U.S. War Department across the Army, Navy, and Air Force. The Rio Rancho-based company announced two new prototype agreements with the Air Force under the Counter-Air Missile Program on Monday. These deals cover the design, construction, and flight testing of a ground-launched counter-air missile, a launch pod, and a containerized launcher.
The company is currently preparing for production on Project Ranger in 2027. Its parent entity, Castelion, has been expanding its military portfolio. The new Air Force work involves integrating the Blackbeard weapon system onto F-16 fighter jets. Andrew Kreitz, Castelion’s CFO and co-founder, stated on Friday that the company will manufacture Blackbeard at a high rate and integrate it onto various U.S. platforms. He noted that the system is already being deployed on F-18s and the Army’s HIMARS ground-launched platform. The F-16 represents the second aircraft and the first Air Force jet to receive the missile.
Kreitz said the Air Force work will take place at the Project Ranger campus in Sandoval County. The facility is located about three miles west of Rio Rancho. He declined to specify other locations for the counter-air missile work, citing ongoing development. He described the Air Force contract as an ongoing effort spanning approximately two years. The company will conduct multiple cycles of design, building, and flight testing during that period.
Construction on the Project Ranger campus is progressing, though the timeline has shifted. Kreitz said major construction for the first two phases is expected to finish in early 2027. This includes the first 22 buildings on the site. Process equipment installation is scheduled for the first and second quarters of 2027. Internal development builds to begin pressurizing the factory are also targeted for the second quarter. The company reported it is running about one to one and a half months behind schedule on construction and two to three months behind on production equipment. Kreitz said the team built margin into the schedule, so the overall progress remains on track despite the slip.
Hiring for the Rio Rancho facility is underway. The company currently has 25 to 30 employees in New Mexico and about 75 open positions. Kreitz said the company is accelerating recruitment efforts. Initial projections called for 200 to 300 jobs for a single shift operation. The company hopes to expand to three shifts if demand for Blackbeard increases. As production rates rise, Castelion will add capabilities at Project Ranger and hire more workers.
Kreitz expressed confidence in continued political support for the company’s defense work. He recently met with members of both parties in Washington, D.C. He described defense modernization as a bipartisan priority. Both Republican and Democratic lawmakers seek larger scale and lower cost in defense contracts. Kreitz said the company remains optimistic about its trajectory despite recent changes in Congress.