Lawsuit claims 200 million gallons drawn under disputed Project Jupiter permit

Center for Biological Diversity sues state water agency over emergency well authorization near Santa Teresa.

By Paula Delgado ·

Illustration for: Lawsuit claims 200 million gallons drawn under disputed Project Jupiter permit
Illustration generated for this article, not a news photograph.

Project Jupiter has consumed roughly 200 million gallons of water since construction began, according to a lawsuit filed Thursday in state District Court. The complaint targets the Office of the State Engineer and State Engineer Elizabeth Anderson. It also names Santa Teresa Capital LLC as a real party in interest.

The environmental group Center for Biological Diversity alleges an emergency authorization granted in October 2025 broke state law. The agency allowed the project to drill a new well and change water rights usage days after the application was filed. The group argues this process skipped required public notice and a hearing.

The lawsuit cites Office of the State Engineer data showing the water right previously irrigated a single sod farm. That land spans several hundred acres near the project site. The complaint claims the agency rubber-stamped a change of ownership with overly broad terms. It argues the new permit violates the state requirement for beneficial use of water.

Jennifer Bradfute, an attorney for Santa Teresa Capital, dismissed the suit in a written response. She called it a repetition of claims the group brought before the state Supreme Court earlier this year. In that earlier case, justices ordered a stop to pumping in August. They dismissed the case the following month, and water flow resumed.

“Santa Teresa Capital’s water right has been permitted for commercial and industrial use for more than 40 years,” Bradfute said. She noted the land includes the project site. “Now a national advocacy group based in Arizona is asking a court to rewrite a New Mexico water right that the State Engineer permitted decades ago.”

Bradfute stated the only change was replacing a failed well. She said the new well draws from the same aquifer at the same limits. A hearing on the water right change is docketed with the Office of the State Engineer. As of Thursday, a public hearing had not been scheduled.

Sarah Baer, an attorney for the Center for Biological Diversity, said the lawsuit targets the agency’s failure to enforce water laws. She said the process deprived New Mexicans of a voice in how their water is used. “That has deprived New Mexicans of our voice and allowed water that’s supposed to be used for irrigation to be diverted to the highly controversial Project Jupiter construction site,” she said.

A spokesperson for the Office of the State Engineer declined to comment on the new allegations on Thursday. Agency attorneys have defended the permit as legal in recent months. Nat Chakeres, an attorney for the office, told state legislators last month that staff visited the site in October 2025 before granting emergency authorization. He said the company did not ask for a change in the purpose of use.

Chakeres argued settled law allows holders of commercial water rights to sell water at the wellhead. He described the developers' plan to use about 750 acre-feet of water for construction. That volume equals approximately 244 million gallons. “I think they’ve done the community a disservice, through failure to be fully transparent on water needs and uses,” Chakeres said during the legislative committee meeting.

More News · Albuquerque news · Report a business · Got a Story?

Get Bernalillo Herald in your inboxLocal news for Bernalillo County, New Mexico. Free, a few times a week, unsubscribe any time.

Get Bernalillo Herald in your inboxLocal news for Bernalillo County, New Mexico. Free, a few times a week, unsubscribe any time.